KBH Haus was awarded this project following tender submission. The project started with an Asbestos Survey, to which Asbestos was identified. This was removed by our approved Asbestos Removal contractor.

KBH Haus was awarded this project following tender submission. The project started with
an Asbestos Survey, to which Asbestos was identified. This was removed by our approved Asbestos
Removal contractor. A Waste Consignment note and Air Test Certificate were issued to Newham Council.
Scaffolding was erected, and a temporary roof was installed to ensure that there was no water ingress to
the property. We installed new felt batten and a slate finish. We worked alongside building control and
the roof was signed off by building control upon completion.

Logo of Newham
Employer:Newham
Service:Responsive
Capability:Routine Maintenance & Repairs
Stage:
Completed
Area:Ealing
Value:£22,000
Start:March 2021
Completion:April 2021

Share on:

Latest Case Studies from our Project Portfolio

Cupboard Door Maintenance
Responsive
Cupboard Door Maintenance
Front Access Ramp & Enabling Works
Responsive
Front Access Ramp & Enabling Works
Window Repair
Planned Works
Window Repair